Earth Moving Material Projects


Location: Boston, MA
Client: Massachusetts Water Resources Authority
Contract Amount: $49,800,000

Work involved excavation and movement of approximately 4,000,000 CY of glacial till and 1,400,000 tons of tunnel muck. Approximately 2,000,000 CY of glacial till was removed all by barge and disposed of off Deer Island with most of it being used as capping material for landfills.